Belfast Sewer – complete overhaul

Belfast Sewer works

The £100m stormwater managment scheme for Northern Ireland Water called on LBA to help to modernise the Victorian infrastructure of Northern Ireland’s leading city.

Project Details

Client NIW
Date 2009
Skills Tunnelling,  Geotech Engineering
Value Est. £100m

Project Description: Belfast, in common with many UK cities, has an old, largely Victorian sewer network, incorporating combined sewer and stormwater flows. The system has a limited capacity and regularly overflows, leading to flooding of low lying areas of the city. The Belfast Sewers scheme was proposed in order to significantly reduce the number of these flooding events and improve the water quality in the River Lagan, which flows through Belfast.

Northern Ireland Water (NIW), the Client, appointed Atkins to produce the reference design for the solution, a £100m stormwater management scheme, which was put out to tender for a design and build contract under NEC Option C. A Joint Venture, consisting of Morgan Est and Farrans was appointed Contractor in August 2006, with Morgan Est’s design arm UPS appointed as their Designer. Atkins was retained as the Project Manager. Some 9.4km of tunnels were required, picking up 10 Combined Stormwater Outfalls, and producing a total storage capacity of 85,000m3. It is predicted that the scheme will be utilised around 15 times each year, taking a total annual flow of around 826,000m3.

Variable Geology

With highly variable geology well beneath the water table, Earth Pressure Balance (EPB) TBMs were employed on all of the drives, with the bulk of the tunnelling carried out by two Lovats: a 4.0mID; and a 2.44mID. Many modifications were made to the cutterheads to cope with the changes from alluvium to sandstone and the occasional extremely hard dolerite dykes, and on a number of occasions significant works were required during tunnelling, at times using compressed air (requiring bulkheads to be placed within the tunnel). The south eastern branch in Ormeau Park was to be driven with less cover and through the Upper Boulder Clay. Pipejacking was adopted, using a 2.1mID Lovat EPB, which struggled through large numbers of wheelbarrow-sized boulders, often found in clusters or ‘nests’. The shaft locations were defined in order to intercept the 10 major stormwater overflows, with an additional 3 shafts for inspection and escape purposes. All shafts were sunk as dry caissons with local dewatering of the lower aquifer. An in-situ concrete lining was placed in the lower section of each shaft. The 38m diameter, 40m deep Tunnel Pumping Station (TPS) was constructed using diaphragm walls to rock level and a sprayed concrete lining (SCL) below, with an in-situ concrete secondary lining to ensure a smooth interior. A central wall divides the shaft into dry and wet wells, the dry well housing pumps and pipes capable of 16m3 m/s. Tunnelling was completed in September 2009, and the TPS pumps commissioned in October 2009.

LBA Role

LBA worked with Atkins, Northern Ireland Water’s project managers, provided managerial assistance and support from June 2007 to the end of 2009. We also provided a Tunnels Inspector for the duration of the project.

Project Highlights

The tunnels passed beneath, or near to, 240 properties, including sensitive offices, churches and the landmark Albert clock (which has already suffered from the inadequate bearing capacity of the Sleech and had a pronounced lean pre-tunnelling). High quality and joined up stakeholder management and public relations from all parties were key to the project success, building on early engagement, information dissemination, open and honest communications, and prompt and positive reaction to concerns. Shaft 7 at the tunnel bifurcation was situated very close to residential and business properties including hotels, and therefore an acoustic shed was built over the shaft head in to permit 24-hour working. A high-angle conveyor (HAC) was installed here and coped well with the varied ground conditions. Compressed air workforce monitoring included MRI scanning in a trial to replace the more traditional long bone X-rays.

A section of the tunnel alignment and one shaft fell within the footprint of an old gas works, where testing showed the groundwater to contain toluene, xylene, and benzene. Shaft sinking progressed well, with the dewatering water passing through a treatment plant, and low levels of residual hydrocarbons in the shaft requiring protective equipment and filtration masks only. It was thought that tunnelling would be below the contamination level, but this proved not to be the case. Extensive mitigation measures were required including continuous monitoring, chemical oversuits and heavy filtration or fresh air supply masks, significantly reducing production rates.

 

 

s

Belfast Sewer Contamination

Extensive mitigation measures were required including continuous monitoring, chemical oversuits and heavy filtration or fresh air supply masks, significantly reducing production rates.

Construction Planning

Brilliant planning saves money and time

Engineering Solutions

Engineering Solutions for your civil project

Commercial Services

More about our commercial services

Project Management blurb icon

Project Management

LBA’s PM experience is second-to-none